TOLL SCHEDULE
Effective July 1, 2011 |
| Passenger vehicles, including motorcycles & small trucks less than 7,000 lbs. gross vehicle weight |
$5.00 |
| Trucks, mobile homes and recreation vehicles- gross vehicle weight 7001 pounds and up per axle |
$7.50 |
| 2 axles |
$15.00 |
| 3 axles |
$22.50 |
| 4 axles |
$30.00 |
| 5 axles |
$37.50 |
| 6 axles |
$45.00 |
| Buses - per axle |
$3.75 |
| 2-axle |
$7.50 |
| 3-axle |
$11.25 |
| Extra Axles For Autos (Each) |
$3.75 |
| Extra Axles For Trucks (Each) |
$7.50 |
|
|
Your Toll Dollars at Work
Here are some of the larger capital projects which together total over $1 Billion from our capital plan proposed over the next 5 to 7 years. This plan, this vision, meets our most important responsibility, to assure the safety and security of all who drive across our bridges or ride PATCO.
Benjamin Franklin Bridge
Deck
Truss
Rehabilitation
&
Cable
Dehumidification
-
$30
million
Walt Whitman Bridge
Re-decking/De-leading &
Painting,
Cable
Dehumidification - $216 million
Commodore Barry Bridge
Structural
Repairs - $22 million
Betsy Ross Bridge
Structural
Repairs
&
Bridge
Resurfacing -$26 million
DRPA/PATCO
Rehabilitation
of
the
Fleet - $202 million
|