Bid Opening - CB-20-2010 - Commodore Barry Bridge Substation Relocation To Pier E-10

Date:  April 21, 2011

Time:  10:30 A.M.

Place: Engineering Conference Room South, 7th Floor, OPC

 

                                               

ORGANIZATION

SURETY

PRICE

ESCO Electric

 

 

Aegis Security Insurance Company

$1,737,590.00

The Farfield Company

 

 

Federal Insurance Company

$1,241,000.00

Vanalt Electrical Construction, Incorporated

 

 

Fidelity & Deposit Company of Maryland

$1,118,300.00

Carr & Duff, Inc.

 

 

Western Surety Company

$1,753,000,00

Scalfo Electric

 

 

Great American Insurance Company

$1,065,000.00